Wednesday, October 27, 2010

Boiler Overhaul

Overhaul boiler dilakukan setiap 15 bulan untuk menyambung CF (Certificate of Fittness) atau + 3 bulan + 3 bulan (if approved) 
Langkah2
1)Turunkan firing, stop boiler operation dan cooling down
2) Buat isolation boiler system
3 Open man hole boiler
4)Lakukan boiler pre-inspection (internal)
5)Sekiranya didapati ada defect seperti crack, mesti repair dahulu
6) Buat mekanikal cleaning pada surface, tube dan furnace
7)Final inspection (internal)
8)DOSH inspection
9)Box-up
10)Filling boiler dengan feed water dan leak check
11)Sekiranya DOSH menghendaki Hydro test, blind semua flange dan ikut procedure HT test
12)Flushing all boiler water apabila selesai
13)Filling boiler dan dosing chemical Ammonia dan Hydrazine
14)Start-up boiler
15)Buat recommissioning dan safeguarding test (PSV, Level switch)
16)On-line operation

No comments:

Post a Comment